EICR Certificate Generator/ guides / what is an EICR

What is an EICR?

EICR stands for Electrical Installation Condition Report — the formal document produced when a competent person inspects and tests an existing electrical installation against BS 7671, the IET Wiring Regulations (currently BS 7671:2018 as amended by the 2022 amendment).

What an EICR actually records

An EICR is a condition report, not a certificate of new work. It confirms, as far as reasonably practicable, whether an installation is in a satisfactory condition for continued use, and it records:

The model forms are explicit: the report is only valid when the schedules are attached. A one-page "certificate" without test results is not an EICR.

EICR vs EIC vs Minor Works vs Building Regulations notification

DocumentUsed for
EICR — Electrical Installation Condition ReportReporting on the condition of an existing installation. Periodic inspection.
EIC — Electrical Installation CertificateSafe design, construction, inspection and testing of new work: a new circuit, a full rewiring, a new distribution board or a complete new installation.
Minor Electrical Installation Works CertificateA single circuit addition or alteration — a new socket, a replacement accessory that changes the circuit.
Building Regulations notificationSeparate from BS 7671 paperwork: notifiable work in England/Wales must be registered with a competent-person scheme or Building Control. A landlord's periodic EICR does not notify anything.

Who may produce one

BS 7671 requires the inspection to be carried out by a skilled person competent in electrical inspection and testing. In practice that means a qualified electrician with the right test instruments and calibration — most commonly registered with NICEIC, NAPIT or ELECSA. Scheme membership is not legally mandatory, but letting agents, insurers and local authorities normally expect a registered electrician's report.

The person who signs Section G ("inspected and tested by") takes professional responsibility for the inspection, the test values and the classification codes. Software — including our EICR certificate generator — produces the paperwork; it does not replace competence.

When an EICR is required or expected

What happens after the report

If the overall assessment is Unsatisfactory, at least one observation was coded C1, C2 or FI (see what the codes mean). C1 means danger present now; C2 means potentially dangerous and urgent; FI means investigate without delay. For rented homes, landlords must arrange further investigation or remedial work and provide written confirmation within 28 days of the request. A report with only C3s remains Satisfactory — the improvements are recommendations, not defects.

← All EICR guides · Generate an EICR PDF now · Check when your next one is due